Under the draft, a new concrete plant will need underground storage at an estimated cost of about NIS 1.36–1.81 million, and an existing plant will need roofing and misting systems at an estimated NIS 425,000–710,000 – according to Ministry of Environmental Protection estimates
According to the report's estimates, one-time cost per plant:
| Existing plant: roofing, misting and automatic wheel washing – small plant | ~425,000 ₪ |
| Existing plant: roofing, misting and automatic wheel washing – large plant | ~710,000 ₪ |
| New plant: underground receiving bays – small plant | ~NIS 1.36 million |
| New plant: underground receiving bays – large plant | ~NIS 1.81 million |
| Ongoing maintenance and emissions reporting (existing plant) | ~NIS 12,000 a year |
On the other hand, moving to underground storage is expected to save a plant about NIS 400,000 a year in operating costs for heavy equipment (loaders), so that in the long run a large part of the investment is offset. In addition, cement suppliers and cement storage silos are not affected by the underground storage requirement – the emission limit for silos stays unchanged (10 mg/Nm³); only the limit at truck-mixer loading stations was updated from 50 to 20 mg/Nm³.
In the public consultation documented in the report, the industry argued that actual costs are higher than the estimates – both for the roofing itself and for indirect costs such as betterment levy, municipal tax and planning expenses. At the national level, the report estimates a net cost of about NIS 31 million through 2050, against economic savings of about NIS 58 million from reduced emissions.
The current framework conditions for concrete plants (from 2018) distinguish between plants in a "sensitive area" – within 150 metres of residential, public or leisure buildings – and plants in a "regular area". Only about 5% of plants in Israel are currently classed as being in a "sensitive area".
The proposed update abolishes this distinction entirely. All concrete plants, including those operating as suppliers of ready-mix concrete and anyone storing quarry aggregates on site, will have to meet the same strict level of requirements, regardless of distance from residential areas.
The three main changes: roofing and enclosing all receiving and storage bays (not only receiving bays, as today), automatic misting/spraying/extraction systems in all bays, and automated truck wheel-wash systems at the plant exit.
| Ready-mix concrete plants in the directory | 188 |
| Haifa & the North | 79 |
| Sharon & Gush Dan | 38 |
| Jerusalem & the Shfela | 27 |
| Be'er Sheva & the South | 44 |
Figures from the Israel Concrete directory of concrete plants, November 2026. Because the draft abolishes the distinction between a "sensitive area" and a "regular area", the new requirements will apply to all plants – not only to the roughly 5% currently located in sensitive areas.
| Existing plants | Roofing + misting within 3 years |
| New plants (no building permit by 1.7.2026) | Underground storage only |
| Temporary plants (up to 6 years) | Exempt from the underground storage requirement |
Under the draft, a new business that has not received a building permit by 1 July 2026 must build underground bays only, and above-ground storage of aggregates will not be allowed. Such plants will have to give up open stockpiles of aggregates and quarry sand entirely and move to underground receiving bays only – a change intended to reduce the movement of heavy mechanical equipment on site, one of the main sources of emissions.
A temporary plant set up on a construction site for a building or infrastructure project and intended to be dismantled when it ends is exempt from building underground bays – for up to 6 years, subject to submitting a work plan and a completion timetable. An existing plant with a valid business licence will have to meet the roofing and enclosure requirements within 3 years of receiving the conditions, and the approving authority may require this earlier if there is a concern of strong and unreasonable air pollution.
Source: Regulatory impact assessment – updated framework conditions for concrete plants, Ministry of Environmental Protection, February 2026 – circulated for public comment on the government memoranda site (tazkirim.gov.il, in Hebrew); and the draft framework conditions – item 10.7a, concrete, Ministry of Environmental Protection (version for public comment). Plant numbers are from the Israel Concrete directory, November 2026. The information is presented as processed and summarised by Israel Concrete.